Case study: a faster shift start at a cement captive mine

{{ answer }}

01 Problem

The first half hour of every shift was lost

Operators punched in late and the first dumper reached the shovel well after shift start. Nobody had a daily number for it, so it was never managed.

32 min
time to first load at the start
02 Setup

Punch-in joined with GPS

Biometric punch-in times were matched with the first GPS trip of each operator's machine. The gap between shift start, punch-in and first load became a daily report per shift and per operator.

~150,000
trips analysed
Jan–Sep 2026
period
Fleet management →
03 Result

Twenty points more on-time, fifteen minutes back

Supervisors used the daily report to follow up late starts. On-time punch-in rose for every shift, with the largest gain on shift A.

63% → 83%
on-time punch-in
48% → 74%
shift A on-time punch-in
32 → 17 min
time to first load

Questions about shift start case study