What an excavator breakdown costs per hour, worked out from your own numbers

An excavator breakdown costs the production it stops plus the cost of everything waiting on it. Tonnes lost per hour are the excavator's output in tonnes per hour, if no other machine picks up the work. Multiply by your value or margin per tonne, add the hourly cost of idle dumpers and operators, then add the repair. Use your own figures, not an industry average.

Excavator at the face, whose breakdown cost per hour stops the haul fleet
01 Why it matters

One excavator stops a whole fleet

At most opencast mines one excavator feeds a group of dumpers. When it stops, those dumpers either wait or are moved to another face, which takes time. The breakdown cost is therefore larger than the repair bill. It is the production lost at the face plus the cost of the fleet standing around it.

02 Step 1

Tonnes lost

Tonnes lost = excavator output in t/h × minutes stopped ÷ 60. Use the excavator's real average output from your own trip or production records, not the brochure figure. If another excavator absorbs part of the work, subtract the tonnes it moved for this fleet during the stop.

03 Step 2

Value of those tonnes

Value lost = tonnes lost × value per tonne. For ore going to your own plant, use the margin per tonne or the cost of the clinker or product not made. For overburden, the tonnes are not sold, so the cost is the schedule slip: the hours you will later pay for to catch up. Pick one basis and use it every month so the numbers compare.

04 Step 3

Idle fleet and people

Add the hourly cost of every dumper that waits: hire rate or owning cost per hour, diesel burnt idling and the operator's wage. A dumper idling still burns fuel. Multiply by the hours each waited, which you can read from trip and idle records if the dumpers carry GPS.

05 Step 4

Repair and the total

Add parts, labour and any service visit for the repair itself. The total breakdown cost is value lost plus idle fleet cost plus repair. Divide by hours stopped for a cost per hour. Repeat for a month of breakdowns and you have the figure that justifies preventive maintenance or a standby machine.

06 Run it

Run the numbers in the calculator

The ROI calculator's lost production block does steps 1 and 2 from four inputs: stops per month, average minutes per stop, excavator output in t/h and your value per tonne. It uses only your inputs. Enter the minutes you think faster response could recover, and it shows the recovered value too.

Open the ROI calculator →
07 Reducing it

Making breakdowns shorter and rarer

The minutes per stop shrink when breakdowns are logged with their cause the moment they happen and the workshop is told at once. Stops become rarer when service is due by hour meter and telemetry warns before a failure. Minocular records each breakdown, its cause and duration, and tracks availability per machine.

How to reduce HEMM downtime →
Mohit Sahu, Co-founder and Tech Lead, Minocular
About the author

Mohit Sahu

Mohit is a mining engineering graduate of NIT Raipur. He leads Minocular's product and engineering, from fleet dispatch to the drone and AI platforms.

Questions about excavator breakdown cost

How do you calculate the cost of an excavator breakdown?

Multiply the excavator's output in tonnes per hour by the hours stopped to get tonnes lost, then by your value or margin per tonne. Add the hourly cost of idle dumpers and operators, and the repair cost.

What output figure should I use for the excavator?

Use the real average output from your own trip or production records for that machine and material. Brochure figures are usually higher than what a machine achieves at a given face.

How do I value lost overburden tonnes?

Overburden is not sold, so value it as the cost of catching up later: the extra machine hours and diesel needed to recover the schedule. Use the same basis every month.

Should idle dumpers be included in breakdown cost?

Yes. Dumpers waiting on a stopped excavator still cost their hire or owning rate, idle diesel and operator wages. GPS idle records show how long each one waited.

Is there an average cost per hour for an excavator breakdown?

There is no figure that fits every mine, because output, value per tonne and fleet size differ. Work it out from your own numbers with the method above.

How can a mine reduce excavator breakdown cost?

Log each breakdown with its cause at once so the workshop responds faster, schedule service by hour meter, and use telemetry warnings to catch failures early.

Related
TOOL
Mining ROI calculator
GUIDE
Reduce HEMM downtime
CAPABILITY
Workshop and maintenance
BLOG
Match factor in mining
See every breakdown, its cause and the hours it cost.
Book a Demo