Plan vs actual tonnes in mining: budget, shift target and what was moved

Plan vs actual in mining compares the tonnes a mine planned to move with the tonnes it actually moved, for each shift, day and month. The plan comes from the annual budget broken down into monthly and shift targets. The actual comes from counted trips, weighbridge tickets or survey. The gap only helps when it can be traced to machines, hours and delays.

Control room screen comparing plan vs actual tonnes in a mine
01 Definition

What plan vs actual means at a mine

Plan vs actual is the comparison of planned production with achieved production over the same period. At an Indian opencast mine the plan usually starts as the annual budget in tonnes of ore and overburden. It is then split into monthly targets and shift targets for each pit, bench or contractor. The actual is what the mine reports as moved in that shift, day or month.

02 Budget, plan, target

Budget, plan and shift target are different numbers

The budget is fixed for the year and drives the money. The mine plan changes as benches, grades and machines change. The shift target is what the control room is asked to deliver today. A mine that compares actuals only to the budget finds out late. Comparing each shift with its own target shows the slip while there is still time to recover it.

03 Where actuals come from

Where the actual tonnes come from

Actual tonnes are counted in three common ways. Trip counts multiply trips by a factor tonnage per dumper. Weighbridge tickets give weighed tonnes for material that crosses a weighbridge. Drone or ground survey measures volume moved over a longer period. Each has a different lag and error, so many mines reconcile trip tonnes against weighbridge and survey at month end.

04 Explaining the gap

Why a gap number alone does not help

A shortfall of a few thousand tonnes says nothing about the cause. The cause is usually an excavator down, dumpers waiting in a queue, a long haul after a bench change, a crusher stop or a late shift change. When every trip is recorded against its excavator, dumper, route and time, the shortfall can be split into these causes and the next shift can act on the biggest one.

The five parts of a haul cycle →
05 Cadence

Shift, day and month views

The shift view is for the control room: target, achieved so far and the rate needed to close the gap. The daily view is for the mine manager: achieved against target by pit, material and contractor. The monthly view is for head office: actuals against budget and the reconciliation between trip, weighbridge and survey tonnes.

06 In Minocular

Shift targets next to live production

Minocular's operations dashboard shows daily production and quality figures for the shift and cumulative, so the control room can see whether the shift is on target. Reporting and analytics compile production, fleet, fuel and downtime per shift into scheduled reports, so the daily and monthly comparison does not need to be rebuilt by hand.

See the operations dashboard →
Mohit Sahu, Co-founder and Tech Lead, Minocular
About the author

Mohit Sahu

Mohit is a mining engineering graduate of NIT Raipur. He leads Minocular's product and engineering, from fleet dispatch to the drone and AI platforms.

Questions about plan vs actual in mining

What is plan vs actual in mining?

Plan vs actual compares the tonnes a mine planned to move with the tonnes it actually moved over the same shift, day or month. It shows whether production is on track against the shift target and the annual budget.

What is the difference between budget and plan in a mine?

The budget is the yearly production figure that drives the money and stays fixed. The mine plan changes with benches, grades and machines, and is split into monthly and shift targets.

How are actual tonnes measured in a mine?

Actual tonnes come from trip counts multiplied by a factor tonnage, from weighbridge tickets, or from drone and ground survey. Many mines reconcile the three at month end because each has a different lag and error.

Why compare actuals with the shift target and not just the budget?

Comparing with the budget only shows a shortfall at month end. Comparing each shift with its own target shows the slip while the next shift can still recover it.

What causes a gap between plan and actual production?

Common causes are excavator breakdowns, dumpers queuing at the face, longer hauls after a bench change, crusher stops and slow shift changes. Trip-level data shows which of these caused a given shortfall.

Can plan vs actual reports be produced automatically?

Yes, if production is recorded trip by trip. Shift and daily reports can then be compiled and emailed on a schedule instead of being built in a spreadsheet.

Related
CAPABILITY
Mine operations dashboard
CAPABILITY
Mine production reporting
SOLUTION
Fleet management
BLOG
Match factor in mining
See each shift's target next to the tonnes actually moved.
Book a Demo